Please can we book the Pavilion???

I’m sure you have been following the build progress for our exciting project to upgrade the pavilion building on Mill Lane Playing Fields. There will be a larger hall, a fully fitted bar and a commercial specification kitchen. Upstairs the two smaller rooms will be redecorated and the balcony has been significantly extended over the new foyer and hall extension.

We will be actively encouraging community use of the facilities alongside the sports requirements of the existing clubs. At this point, we do not have visibility of the 2026 fixtures for the sports clubs so we are not currently in a position to offer bookings for other users of the hall just yet. As soon as we have a calendar of available dates and times for rooms in 2026 we will be able to offer them for booking. Please watch this space!

Our launch event for the pavilion is planned for Monday 4th May. If you would like to come along on that date we can show you around and you can see all the new and refurbished facilities first-hand.

We look forward to welcoming you to the pavilion.

Similar Posts

  • News Update Headley Pavilion June 2025

    The team from Flint Construction have been very busy in the last month and we are now seeing things appearing that weren’t there before! The rearrangement and additions of changing rooms, storage and toilets has needed new internal walls, so the bricklayers have been making new block walls and sealing up windows and door spaces…

  • News Update Headley Pavilion July 2025

    Every month, two Headley Parish Councillors attend a full Site Meeting at the Headley Pavilion with the architect, Flint Construction, the sub-contractors and consultants. This ensures that there is full and open discussion between HPC as the client, the suppliers and professional advisors. This also means that queries can be resolved quickly and decisions taken…

  • Headley Pavilion Project – News Update May 2025

    They say things have to get worse before they get better and that’s very true of any rebuild project! First of all, the premises have to be emptied, then all the areas of the building inside and outside have to be stripped out or demolished. Flint Construction have been busy doing just that, so although…

  • News Update on the Headley Pavilion November 2025

    Heading photo: the all-new foyer and hall extension with balcony above. The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the…

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…

  • PEG Working Party at Standford Green

    This week Cllr. Steve Thair organised a working party of Headley’s Parish Enhancement Group members to clear the pathway that runs from Standford Green to the Hatch Farm Watermeadows. This is a permissive path and the surrounding vegetation had become very overgrown along its length. With the kind permission of the landowner, Cllr. Steve Thair,…