The team from Flint Construction have been very busy in the last month and we are now seeing things appearing that weren’t there before! The rearrangement and additions of changing rooms, storage and toilets has needed new internal walls, so the bricklayers have been making new block walls and sealing up windows and door spaces that are no longer required. The foundations for the new extensions are in place, and we could see wiring and pipework being installed so that it will be hidden within the new walls and ceilings.

As expected with any major refurbishment, when you remove surface coverings the underlying structure may not be as sound as first hoped, so we may have to do more work to bring the building up to standard. However, this possibility had already been factored into the plans so that shouldn’t cause a delay in the project.

We have also been helping with the fun stuff, which is choosing the colour schemes for the welcome areas, changing rooms and toilets. No more painted blockwork! When the building is completed, we will only see the paint and tiles not the brick and concrete below so although decoration is a tiny part of the overall project cost, it is very important that it creates the right impression.  Here are a few pictures from the work inside the building.

Similar Posts

  • Please can we book the Pavilion???

    I’m sure you have been following the build progress for our exciting project to upgrade the pavilion building on Mill Lane Playing Fields. There will be a larger hall, a fully fitted bar and a commercial specification kitchen. Upstairs the two smaller rooms will be redecorated and the balcony has been significantly extended over the…

  • News Update Headley Pavilion August 2025

    The Flint Construction team have been making great progress and the overall shape of the new building is clearly visible. The heading photo shows the new entrance foyer leading into the extended hall space. We previously had concerns about the condition of the hall floor under the vinyl covering, and when this was lifted it…

  • News Update on the Headley Pavilion Project – February 2026

    Heading photo: Students from Alton College making a video of the site construction. Last month we reported that the number of visible improvements was accelerating, and this has continued spectacularly. With only a couple of weeks to go to handover, the Flint Construction team are hard at work putting the final fixtures and fittings in…

  • Headley Pavilion Project – News Update May 2025

    They say things have to get worse before they get better and that’s very true of any rebuild project! First of all, the premises have to be emptied, then all the areas of the building inside and outside have to be stripped out or demolished. Flint Construction have been busy doing just that, so although…

  • VACANCY FOR PARISH COUNCILLOR

    We currently have a vacancy for a Parish Councillor. If you are care about your community and the village you live in, we’d love to hear from you. Being a councillor is a rewarding way to help shape the place you live and work. As a Parish Councillor, you’ll have the opportunity to: No prior…

  • Introducing…The Parish Enhancement Group!

    The role of Headley Parish Council is very broad, so it makes sense to divide the activities up into dedicated Working Groups. These are not formal committees: the emphasis is on getting things done, not endless meetings! The Parish Enhancement Group (PEG) consists of five councillors and soon we hope, members of the local community…