News Update Headley Pavilion July 2025

Every month, two Headley Parish Councillors attend a full Site Meeting at the Headley Pavilion with the architect, Flint Construction, the sub-contractors and consultants. This ensures that there is full and open discussion between HPC as the client, the suppliers and professional advisors. This also means that queries can be resolved quickly and decisions taken to avoid delays. For example, this month we became aware that the main hall floor concrete was not in good condition. We had to make the decision to incur the cost of re-screeding the floor to ensure it stands up to future wear. Because we had the electrical and plumbing contractors in the room we quickly realised that we can now hide pipes and cables under the new concrete. Although re-screeding is an additional cost, it has the added advantage that we won’t have ugly pipe and cable conduits running across the walls as we had before.

One of the complaints about the original pavilion was unreliability of the drains which often backed up or blocked. We have done a thorough investigation of the drainage system and made a number of improvements. This means the drains will be able to cope with the expected use and will also be easier to access if there is a problem in the future.

The inside walls have now been completed so the most visible progress in the last month has been outside the building. The 4,600 litre rainwater harvesting tank has been installed in a big hole and covered over. All you can see now is a manhole cover and the pipework for the control box!

The walls to the new foyer and hall extension are almost complete, and you can now see the size of the new balcony above. Walls to the extension at the car park end are 75% complete. Scaffolding is in place for the roof repairs which start this month and on completion this will be followed by the installation of the solar panels. We have also finalised the designs for the new kitchen area and bar fit-out which will be a huge improvement over the previous facilities for catering.

Although we have a few “unexpected extras” to deal with, we have also identified some savings so overall the project remains on budget and progressing according to plan.

Heading photo: Cllr. Deborah Chamberlain signing in at the construction Site Office for the monthly meeting.

Neville Merritt
July 2025

Similar Posts

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…

  • Headley Pavilion Grand Opening and Here’s Headley Show

    What a wonderful day we had on Bank Holiday Monday 4th May. The combination of Here’s Headley, the Grand Opening of Headley Pavilion, glorious weather and hundreds of visitors made it a memorable occasion. After a rousing call to action from Frankie Milam, our Headley Bagpiper, Cllr. Mark Dickens Chairman of Headley Parish Council welcomed…

  • Do you have ideas for Community Use of the Headley Pavilion?

    When the upgraded Headley Pavilion is reopened early in 2026, it will have some wonderful new facilities for both sporting and non-sports use. This includes an extended hall, new kitchen, bar, outdoor areas and of course improved changing rooms and toilets in addition to the upstairs rooms which will be available for booking. Opportunities include…

  • News Update Headley Pavilion August 2025

    The Flint Construction team have been making great progress and the overall shape of the new building is clearly visible. The heading photo shows the new entrance foyer leading into the extended hall space. We previously had concerns about the condition of the hall floor under the vinyl covering, and when this was lifted it…

  • News Update on the Headley Pavilion November 2025

    Heading photo: the all-new foyer and hall extension with balcony above. The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the…

  • News Update on the Headley Pavilion Project January 2026

    A highlight of December was hosting a visit from over 50 pupils from The Holme School, Headley. Site Manager Neil Kelly with his team and Gordon Kerr the architect had prepared a guided tour to show the children what goes on behind the safety fence around a busy building site. They also explained how the…