News Update Headley Pavilion August 2025

The Flint Construction team have been making great progress and the overall shape of the new building is clearly visible. The heading photo shows the new entrance foyer leading into the extended hall space.

We previously had concerns about the condition of the hall floor under the vinyl covering, and when this was lifted it was confirmed that the concrete below was in poor condition. Having looked at a number of repair options none of which were guaranteed, we decided to dig up the entire floor and re-screed it. Although this is an additional expense, it has the advantage that we can bury heating pipes under the floor instead of running them along the walls, and we can install an induction loop for the audio system.

We have also been reviewing colour schemes for the public areas including options for a more dramatic wall treatment in the entrance foyer. We want it to be exciting, welcoming and inclusive so the choices here are very important even though it’s only paint!

When you are involved in a project of this scale, you realise just how many decisions have to be made even after the design is finalised. Our days are never without exchanges of emails between the builders, consultants, architect and Headley Parish Council about colours of railings, type of radiator, location of pipes and much, much more. It really is a team effort from all involved.

Despite the additional work on the hall floor, the project remains on budget and progressing according to expected timescales.

Neville Merritt
August 2025

Similar Posts

  • Introducing…The Parish Enhancement Group!

    The role of Headley Parish Council is very broad, so it makes sense to divide the activities up into dedicated Working Groups. These are not formal committees: the emphasis is on getting things done, not endless meetings! The Parish Enhancement Group (PEG) consists of five councillors and soon we hope, members of the local community…

  • News Update on the Headley Pavilion September 2025

    The rate of progress is impressive. When we attend the monthly site meetings it seems like we are entering a different building! All the ground work (drains etc.) is complete, the new flat roof and balcony is complete, the roof repairs have been done and tiling was completed at the end of August. Electrical installation…

  • News Update on the Headley Pavilion November 2025

    Heading photo: the all-new foyer and hall extension with balcony above. The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the…

  • Headley Pavilion Project – News Update May 2025

    They say things have to get worse before they get better and that’s very true of any rebuild project! First of all, the premises have to be emptied, then all the areas of the building inside and outside have to be stripped out or demolished. Flint Construction have been busy doing just that, so although…

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…

  • Headley Pavilion Grand Opening and Here’s Headley Show

    What a wonderful day we had on Bank Holiday Monday 4th May. The combination of Here’s Headley, the Grand Opening of Headley Pavilion, glorious weather and hundreds of visitors made it a memorable occasion. After a rousing call to action from Frankie Milam, our Headley Bagpiper, Cllr. Mark Dickens Chairman of Headley Parish Council welcomed…