Headley Pavilion Project – News Update April 2025

The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of this type of work.

On 26th March we held a “Pre-Commencement Meeting” where we sat around a (very large) table with the team from Flint, the main sub-contractors, our Project Architect, the Quantity Surveyor and representatives from HPC as the Client. This is where we start getting down to details – what will go where, any changes to specification etc. so all the pipes and wires will end up in the right place.

You may have noticed people working on the roof recently and this was a survey to confirm what needs to be done. We have also seen the proposals for the interior fit-out and colours, and I think it’s going to be an amazing transformation!

During early April, the last of the contents of the Pavilion will be removed and it will be closed from 7th April onwards. The contractors will arrive on site on 14th April and a security fence will be erected around the Pavilion and most of the main car park so the playing fields can still be used. Temporary toilets will be installed and these are for club use only.

Signs will be placed at the Playing Fields access points warning of the construction works taking place. Public access will continue to be available as before, and the Tennis and Bowls club activities will be largely unaffected.  We ask that all visitors to the Playing Fields keep clear of construction work and vehicles for their own safety. Parking in the lane and the Junior Football Field car parks are for club members only. Public parking will be very limited for the duration of the construction work.

We expect the work to be completed by the beginning of 2026, and we will be publishing monthly updates as work progresses. We are extremely fortunate to be able to do such a major upgrade of facilities for Headley and we are very grateful to all those who have put it such a lot of effort to bring it this far.

Similar Posts

  • News Update Headley Pavilion August 2025

    The Flint Construction team have been making great progress and the overall shape of the new building is clearly visible. The heading photo shows the new entrance foyer leading into the extended hall space. We previously had concerns about the condition of the hall floor under the vinyl covering, and when this was lifted it…

  • Please can we book the Pavilion???

    I’m sure you have been following the build progress for our exciting project to upgrade the pavilion building on Mill Lane Playing Fields. There will be a larger hall, a fully fitted bar and a commercial specification kitchen. Upstairs the two smaller rooms will be redecorated and the balcony has been significantly extended over the…

  • News Update on the Headley Pavilion September 2025

    The rate of progress is impressive. When we attend the monthly site meetings it seems like we are entering a different building! All the ground work (drains etc.) is complete, the new flat roof and balcony is complete, the roof repairs have been done and tiling was completed at the end of August. Electrical installation…

  • Do you have ideas for Community Use of the Headley Pavilion?

    When the upgraded Headley Pavilion is reopened early in 2026, it will have some wonderful new facilities for both sporting and non-sports use. This includes an extended hall, new kitchen, bar, outdoor areas and of course improved changing rooms and toilets in addition to the upstairs rooms which will be available for booking. Opportunities include…

  • News Update on the Headley Pavilion Project – February 2026

    Heading photo: Students from Alton College making a video of the site construction. Last month we reported that the number of visible improvements was accelerating, and this has continued spectacularly. With only a couple of weeks to go to handover, the Flint Construction team are hard at work putting the final fixtures and fittings in…

  • News Update Headley Pavilion Project March 2026

    As anyone who has had any major work done on their house will know, there isn’t an exact moment when it is “finished”! The Flint Construction team worked extremely hard to get everything ready for the scheduled handover in February, and all of their work inside the building was completed. Unfortunately, due to the weather,…