Headley Pavilion Project – News Update April 2025

The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of this type of work.

On 26th March we held a “Pre-Commencement Meeting” where we sat around a (very large) table with the team from Flint, the main sub-contractors, our Project Architect, the Quantity Surveyor and representatives from HPC as the Client. This is where we start getting down to details – what will go where, any changes to specification etc. so all the pipes and wires will end up in the right place.

You may have noticed people working on the roof recently and this was a survey to confirm what needs to be done. We have also seen the proposals for the interior fit-out and colours, and I think it’s going to be an amazing transformation!

During early April, the last of the contents of the Pavilion will be removed and it will be closed from 7th April onwards. The contractors will arrive on site on 14th April and a security fence will be erected around the Pavilion and most of the main car park so the playing fields can still be used. Temporary toilets will be installed and these are for club use only.

Signs will be placed at the Playing Fields access points warning of the construction works taking place. Public access will continue to be available as before, and the Tennis and Bowls club activities will be largely unaffected.  We ask that all visitors to the Playing Fields keep clear of construction work and vehicles for their own safety. Parking in the lane and the Junior Football Field car parks are for club members only. Public parking will be very limited for the duration of the construction work.

We expect the work to be completed by the beginning of 2026, and we will be publishing monthly updates as work progresses. We are extremely fortunate to be able to do such a major upgrade of facilities for Headley and we are very grateful to all those who have put it such a lot of effort to bring it this far.

Similar Posts

  • News Update on the Headley Pavilion October 2025

    Heading photo: new hall floor; door and window frames under construction. A lot of building work happens before you can see progress. For the last few months the site has been a flurry of activity but most of the work will end up hidden from view. This month is different, because suddenly we can really…

  • Please can we book the Pavilion???

    I’m sure you have been following the build progress for our exciting project to upgrade the pavilion building on Mill Lane Playing Fields. There will be a larger hall, a fully fitted bar and a commercial specification kitchen. Upstairs the two smaller rooms will be redecorated and the balcony has been significantly extended over the…

  • PEG Working Party at Standford Green

    This week Cllr. Steve Thair organised a working party of Headley’s Parish Enhancement Group members to clear the pathway that runs from Standford Green to the Hatch Farm Watermeadows. This is a permissive path and the surrounding vegetation had become very overgrown along its length. With the kind permission of the landowner, Cllr. Steve Thair,…

  • News Update Headley Pavilion July 2025

    Every month, two Headley Parish Councillors attend a full Site Meeting at the Headley Pavilion with the architect, Flint Construction, the sub-contractors and consultants. This ensures that there is full and open discussion between HPC as the client, the suppliers and professional advisors. This also means that queries can be resolved quickly and decisions taken…

  • News Update on the Headley Pavilion November 2025

    Heading photo: the all-new foyer and hall extension with balcony above. The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the…

  • You can save a tree!

    We are incredibly lucky to live in an area with so many trees for us enjoy and for the benefit of the natural environment. With increasing pressure from housing development, we must do all we can to protect what we have. Fortunately there is legislation for exactly that – the Tree Preservation Order (TPO). If…