News Update on the Headley Pavilion November 2025

Heading photo: the all-new foyer and hall extension with balcony above.

The cooler months are now upon us, and that is good timing for the construction team because most of the external building work has been completed. Most of the scaffolding has been removed, leaving only a small section to enable them to lift the heavy paving slabs onto the new balcony. As soon as that is completed, you will see the railings installed.

The big bifold glass door at the end of the hall is in place, and that will give access from the hall and bar area to an outside patio and path around to the new pétanque terrain. Unfortunately the other main front window and door are delayed at the factory otherwise we could see an almost complete frontage.

Inside the building, the wiring and pipework is being connected up to create the heating, lighting and power systems that will make the building bright and comfortable. Internal painting is progressing and tiling in the shower areas started at the end of October. It will be a far cry from the painted block walls and crumbling tiles that we hadbefore.

Our next site meeting will be mid-November, and by then it’s going to look a lot less like a building site and a lot more like a useable building. I can’t wait to see what the new colour scheme looks like!

The time taken for the hall floor screed to harden has put the construction completion date back to mid-February, but we don’t expect this to affect the planned fit-out and opening dates in 2026. We will be combining the formal opening ceremony with the Here’s Headley celebration of local activities on the Bank Holiday 4th May 2026 at the Headley Pavilion and Playing Fields.

Neville Merritt
November 2025

Similar Posts

  • News Update Headley Pavilion June 2025

    The team from Flint Construction have been very busy in the last month and we are now seeing things appearing that weren’t there before! The rearrangement and additions of changing rooms, storage and toilets has needed new internal walls, so the bricklayers have been making new block walls and sealing up windows and door spaces…

  • PEG Working Party at Standford Green

    This week Cllr. Steve Thair organised a working party of Headley’s Parish Enhancement Group members to clear the pathway that runs from Standford Green to the Hatch Farm Watermeadows. This is a permissive path and the surrounding vegetation had become very overgrown along its length. With the kind permission of the landowner, Cllr. Steve Thair,…

  • Headley Pavilion Project – News Update April 2025

    The past month has been full of activity! After issuing an Invitation to Tender in 2024, the responses were carefully analysed in December and January which resulted in the selection of the most suitable contractor. After finalising contractual and financial details we signed contracts with Flint Construction Ltd., an Alresford-based company with considerable experience of…

  • Headley Pavilion Project – News Update May 2025

    They say things have to get worse before they get better and that’s very true of any rebuild project! First of all, the premises have to be emptied, then all the areas of the building inside and outside have to be stripped out or demolished. Flint Construction have been busy doing just that, so although…

  • Our Wildflower Meadow, June

    Our wildflower meadow is a small area of the Village Gren behind the Childrens’ Playground, which has been set aside and seeded to encourage our native flora to grow. It is fascinating to observe the different flowers that appear through the year, and every month brings new additions to the display. Wildflower meadows don’t usually…

  • News Update on the Headley Pavilion October 2025

    Heading photo: new hall floor; door and window frames under construction. A lot of building work happens before you can see progress. For the last few months the site has been a flurry of activity but most of the work will end up hidden from view. This month is different, because suddenly we can really…