Operation Resilience – ST-EH22071 – Picketts Hill, Headley – Carriageway Surface Repairs – Work Notification

As part of the annual programme of works being undertaken by Operation Resilience, we will shortly be undertaking carriageway surface repairs in localised areas along Picketts Hill, Headley, from Frensham Lane to A325.

This work is in preparation for a proposed surface treatment, which if undertaken, will be carried out during 2022.

The works are currently programmed to start on Tuesday 5th April 2022 and are expected to last for up to 1 day, during which time the road will be closed to through traffic from approximately 07:30 to 18:00hrs each day. The road will be open outside of these hours. For more information – https://one.network/?tm=128034767

Whilst there is an allowance within the time periods shown above for delays, there may be times when we have to postpone works at very short notice; based on the latest weather forecasts, this can occur just prior to works commencing. We will always look to provide up to date information wherever we can, but sometimes these last minute decisions can be difficult to relay to the travelling public in a timely manner. When we can, any significant changes to the scheduled dates will be made clear on the yellow sign boards located at the works limits.

Similar Posts

  • Free parking for Christmas events in Alton

    East Hampshire District Council (EHDC) has teamed up with Alton Town Council to provide free parking in the town to encourage local shopping in the build up to Christmas. Parking will be free in all car parks in the town from 5pm on Friday 19 November for the town council’s ‘A Marmot Family Christmas’ event….

  • Temporary closure of Tulls Lane

    EAST HAMPSHIRE DISTRICT COUNCIL (BORDON: TULLS LANE) (TEMPORARY CLOSURE) ORDER 2021 NOTICE is hereby given that not less than seven days from the date of this notice, East Hampshire District Council pursuant to an arrangement entered into under Section 19 of the Local Government Act 2000, with the Council of the County of Hampshire, intend…

  • Churt Road, Headley – Carriageway Repairs

    As part of the annual programme of works being undertaken by Operation Resilience, we will shortly be undertaking carriageway surface repairs in localised areas along Churt Road, from Glayshers Hill to Hammer Lane. This is in preparation for a proposed surface treatment, which if undertaken, will be carried out during 2021. The repairs are currently…

  • Phillips Crescent, Headley – Carriageway Surface Repairs

    As part of the annual programme of works being undertaken by Operation Resilience, we will shortly be undertaking carriageway surface repairs in localised areas along Phillips Crescent, Headley, from Fullers Vale to End. This work is in preparation for a proposed surface treatment, which if undertaken, will be carried out during 2022. You will receive…

  • Churt Road, Headley – Carriageway Repairs

    The works from Glayshers Hill to Hammer Lane are currently programmed to start on Thursday 8th April 2021 and are expected to last for up to 1 day, during which time the road will be closed to through traffic from approximately 07:30 to 18:00hrs. The road will be open outside of these hours. For more…

  • Churchill Crescent & Phillips Crescent, Headley – Carriageway Surface Repairs

    As part of the annual programme of works being undertaken by Operation Resilience, HCC will shortly be undertaking carriageway surface repairs in localised areas along roads within Headley. This is in preparation for a proposed surface treatment, which if undertaken, will be carried out during 2022. You will receive separate notification for this work. The…